Can I sync only selected list items with ms project tasks on SharePoint 2019?

Frequent Contributor

Hello.

Can I sync only selected list items with ms project tasks on SharePoint 2019?

 

 

2 Replies
best response confirmed by Vasily_Zaytsev (Frequent Contributor)
Solution
Vasily -- I believe that the Sync to SharePoint Tasks List feature is an "all or nothing" feature. This means that when you run the sync, the system synchronizes all of the tasks. I am not aware of any method to do the sync with only selected tasks. Hope this helps.