Calulated date is incorrect

Copper Contributor

My Microsoft Project isn’t working correctly. See line 25 should start 7 days after line 6’s completion date since I have everything marked as auto Schedule. see photo below

project.png

1 Reply
best response confirmed by Dale_HowardMVP (MVP)
Solution

@Jumpstart Admin  not 6SF+7,  Please 6FS+7. have a nice day