Calendar without specific months

Occasional Visitor

Hello Team,

we want to create a calendar without specific months and holidays, because we are in planning now the flow but we don’t know exactly when the work will start concretely.

So, we want to create a calendar with “Week 1”, “Week 2” and so on. Every week should have the 5 working days and Saturday and Sunday.

Is it possible and someone can explain us how to do?

 

Best regards

Daniel

1 Reply

@IngHartmann

 

Don't think you need a different calendar. Change your Gantt Chart timeline to ordinal dates and use Custom Number Fields to display Start & Finish Weeks in place of real dates. 

 

This blog post from 2015 is for Project 2010 but should still work for you. Show Calendar Days instead of Dates in MS Project Schedule columns