I have classes that I am loading into Projects. I set up the project to use "Schedule From Finish Date" so that I can enter the class date and then Projects tells me when I have to start setting up the class (for example send out promotional material 90 days prior to the class) - so backwards scheduling. That is working well but the problem is that I would like to have Projects calculate when to accomplish tasks after the class - so those calculations need to be forward scheduling (for example send in test grades 5 days after the class). Is this possible without changing the project set up to "Schedule From Start Date" after the initial set-up?