Best solution for baseline in PFTW

Contributor

Hi All
We see that PFTW does not support baseline, and the solution is that we have to backup the project's task ids to different regions and then use Power BI to aggregate and build analysis reports.
Do you have the best solution for this backup?

Thanks in advance

 

1 Reply

Hello @daibt ,

That is the only option until Microsoft release a feature for this. Here is an example I wrote about 3 years ago (steps might have changed etc.): https://pwmather.wordpress.com/2020/03/12/extending-projectfortheweb-part7-ppm-cds-msdyn365-powerpla... 

Paul