Forum Discussion

ghiasi-amir's avatar
ghiasi-amir
Copper Contributor
May 23, 2021
Solved

Bcwp problem in microsoft project

In the microsoft project 2019 program in the BCWP column, when considering the high amount for COST ($ 100,000,000,000) and then getting BASELINE, changing the Physical% complete values ​​from 10 to 20 and above does not result in a bcwp value correctly. physical% complete is intended for the EARN VALUE METHOD.
This problem will be sent to you in the form of a video saved in the POWER POINT program. Give me the necessary guidance.
Thank you

  • ghiasiamir -- I ran extensive tests on a task that has such a large Cost value and I can confirm exactly what you are experiencing, as I experienced it as well. This is obviously a bug in the software. I would recommend that you contact Microsoft Support and log this as a bug with them so that they can get it fixed. Until it is fixed, I do not have any workaround. Hope this helps.

7 Replies

  • ghiasiamir -- I do not see any resources assigned to your task. One of the requirements of EVA in Microsoft Project is that you must have one or more resources assigned to each detailed task, and you must set the cost rate for each resource to at least $1.00/hour. Also, did you set the Status Date for the project? That is another requirement. Hope this helps.
    • ghiasi-amir's avatar
      ghiasi-amir
      Copper Contributor
      It is not necessary to assign the resource to the activity and define the use for the resource, but it can enter the amount in the cost column without defining the resource. The status date is also specified. This question was asked by several colleagues, but unfortunately no one was able to answer.
      • Dale_HowardMVP's avatar
        Dale_HowardMVP
        MVP
        ghiasiamir -- I ran extensive tests on a task that has such a large Cost value and I can confirm exactly what you are experiencing, as I experienced it as well. This is obviously a bug in the software. I would recommend that you contact Microsoft Support and log this as a bug with them so that they can get it fixed. Until it is fixed, I do not have any workaround. Hope this helps.

Resources