availability of Sensitivity Label in Microsoft Project

New Contributor

Hi, Is there an option to enable or create sensitivity labels in MS Project.

3 Replies

Can we create some sort of macro in Microsoft project, so that we can create user defined sensitivity labels and we can select the sensitivity as required by the user @Paul Mather 

Hello @Surabhi1515,

If you are using Project Server / Project Online, you could have a Project level custom field that was used to store the sensitivity label - the users could set that. If you are using standalone MS Project / MPP files - many be you could use the project properties to add a new property:

PaulMather_0-1648467971292.png

 

Paul