Jun 13 2022 01:41 PM
Hello,
I am starting to lean Project and I am having a hard time trying to set up to have the following happen.
Task A,B, and C are each set to 5 day duration. They are currently linked so they start one after the other (A-B-C) for a total of 15 days. I am trying to set it up so that if task A is completed early (say 3 days instead of 5) that task B will automatically adjust to show 7 days of availably (5 original plus the 2 from task A). I would like it to adjust for the previous task completing early (or late but I hope that does not happen). Thank you for any help you can provide.
Jun 13 2022 01:48 PM
SolutionJun 13 2022 01:52 PM
Jun 13 2022 01:54 PM