Assignment Units Field Not Displaying Any Values

Iron Contributor

After I added the assignment  units field to my project Gantt View.  No Values are displaying and I can't figure out why.  Anyone know?  See screenshot.

Screenshot 2022-05-23 175045.jpg

1 Reply
best response confirmed by Dale Howard (MVP)
Solution
JBLT83,
That's because the Gantt Chart view is a task view which does not show assignment fields. Switch to the Task Usage view and the Assignment Units will show values on assignment rows.

So why is the Assignment Units field even available in the Gantt Chart view? I have no idea, it's just one of those little quirks about Project.

John
1 best response

Accepted Solutions
best response confirmed by Dale Howard (MVP)
Solution
JBLT83,
That's because the Gantt Chart view is a task view which does not show assignment fields. Switch to the Task Usage view and the Assignment Units will show values on assignment rows.

So why is the Assignment Units field even available in the Gantt Chart view? I have no idea, it's just one of those little quirks about Project.

John

View solution in original post