Feb 19 2022 06:56 AM
I have a task A allocated to John and the duration is 20 days. Assuming task A starts on day 1 and completes in day 20. Then on day 3 John informs me that he will be unavailable from day 12 to day 15 inclusive to work on task A.
As a PM I can update John’s unavailability on task A during the period he mentioned.
I would like to assign this task A during John’s absence to Susan. Susan is also working on other task in the project assuming there is no conflict of time for Susan during John’s absence.
My question is how do I assign Susan to work on Task A from day 12 to day 15 inclusive in MS Project? Do I assign Susan to this task A - BUT only show her availability to this task for the said period or is there a better way of doing this?
Rgds
Feb 20 2022 08:42 AM
SolutionFeb 21 2022 06:57 PM
Feb 22 2022 07:13 AM
Feb 20 2022 08:42 AM
Solution