Assigning cost resources to summary task is grayed out

Copper Contributor

Hi,

I am trying to assign a cost resources to the summery task which I created in resources sheet as "Cost" and gave a group name. I turn into gantt chart and try to assign the resources to the summary task. I noticed that the assign button is grayed out. rest of the resources are good to assign.

 

Please advice what is the fix for this issue.

I am using MSP 2016.

 

Thanks

1 Reply
best response confirmed by Jhonex1 (Copper Contributor)
Solution

@Jhonex1 have you got the Summary tasks option checked under Gantt Chart Format? 

 