Łączenie zadań z MS Project z planem w MS Planner

New Contributor

Szanowni, 

Czy, kiedy i jak mogę połączyć zadanie z MS Project z Planem w MS Planner ?

2 Replies
WaldiK --

Please keep in mind that this is an English language user forum, so please post your questions in English. Thanks to Google Translate, I think I can answer your question. As the software currently exists, the only connection between a Microsoft Project task and a Planner task is when the task is in an enterprise project saved in either Project Server or Project Online. And that connection is only a link in Microsoft Project to the corresponding task in Planner. Hope this helps.

@Dale Howard 

Thanks Dale

I think fixing the problem of accessing Project server will be the solution to my problem. I thought that saving the project file to the Microsoft cloud would be the solution to my problem.
GREETINGS

WaldiK