Project Server 2013: Server Settings
Published Mar 06 2019 01:04 PM 668 Views
Brass Contributor
First published on TECHNET on Mar 19, 2013

In Project Server 2013 we have moved some of the Server Settings options that were familiar to people in Project Server 2010, and in Project Online there are other changes to these server settings due to the nature of the service offering – and the fact that you no longer have to manage the server as we do that for you.  From early feedback it is clear there is still some confusion about the changes so thought I’d post some explanation.  I’ll do a follow up post for Project Online so as not to get too confusing in the one post (I hope) – but here goes for Project Server 2013.


*** Update 3/19 - MVP Alex Burton did a good comparison during the preview, and a neat tool http://epmsource.com/2012/09/08/project-server-2010-2013-preview-setting-comparison/ - thanks for the reminder Alex***



In Project Server 2010 Server Settings was available in the left navigation for administrators and it looked like this:-



And in Project Server 2013 we now have a few different places so find the same settings, and the first challenge can be that we have a stripped down menu and by default and Server Settings is gone from the left navigation.  A couple of solutions to this – either use the EDIT LINKS option to make Server Settings appear on the left – or use the new navigation from the gear icon in the top right and select PWA Settings.



This will bring up the PWA Settings page which may look like this:



I say ‘may look like this’ because some of the options will depend on the permissions mode you are currently using.  This is new to Project Server 2013 and is well described in the TechNet article ‘Plan user access in Project Server 2013’ at http://technet.microsoft.com/en-us/library/fp161361.aspx .   In my screenshot I am in the default, SharePoint Permissions mode – so I am missing a few options compared to the following shot from another instance on my server in Project Permissions mode.



As you can see, with Project Permissions mode comes a new section on Security with the familiar options from the 2010 Security section in the top left of the first screen shot – and a couple of extra options in the Personal Settings – for managing and acting as delegates.  Delegation isn’t a feature that is available when you are using SharePoint Permissions.  Also this shows that Personal Settings is now a subset of PWA Settings and not its own menu option.  The security section isn’t applicable to SharePoint Permissions mode as all control is governed by SharePoint rather than by Project’s groups and categories.  This also covers project sites too – so the User Sync section goes away too in SharePoint Permissions mode.  Also note that what was called Project Sites is now covered by Connected SharePoint sites.


So what are we still missing?  PWA Settings covers the Security, Look and Feel. and Time and Task Management sections but we are missing some options in Workflow and Project Detail Pages, Enterprise Data, Queue and Database Administration and Operational Policies.


Some of these are in the ‘other’ Server Settings page – and there a re a couple of ways to get there and I’m including both just for completeness.  They both come from Central Administration and reflect the fact that these settings are not generally items that the PMO should be needing to worry about but are more for the farm administrator.  The first route starts at Central Administration, General Application Settings from the left navigation.



Then click Manage under PWA Settings.  The other route is via the Service Application , so you would click on Application Management from the left navigation then Manage service application under Service Applications.



Within the Manage Service Applications screen you would click on Project Server Service Application – or just select the row and click Manage



And finally in the Manage Project Web Apps page you would select the Url you wanted to manage and using the drop down menu from that line you would select Manage



The first route is the shortest – but if you already happen to be in the page above then worth knowing about this other route too.  Before moving on from that page though, there is one of our missing options!  Manage Queue Settings for Project Web App!  This is now a farm wide setting rather than a per PWA setting – so it is found on the Manage Project Web Apps page.


This next screenshot is the PWA Settings page and the thing to note is that you are in Central Administration and you can manage settings here for ALL of your PWA sites.  If you used the 2nd option through Manage PWA then the right PWA will be selected – but if you arrived via General Application Settings you will need to check and if necessary change the PWA site for which you wish to manage the settings.  The place to do that is highlighted.



Here we have the other Queue and Database Administration options, with Manage Queue Jobs also available here – and the Operational Policies that were missing from the menu within PWA – and finally the Project Workflow Settings option.  So I think the only things missing are Enterprise Global – and About Project Server.  Enterprise Global is now managed from Project Professional 2013 – from the Info tab of the File menu – under Organizer.  About Project Server does not have an equivalent option in Project Server 2013.



As mentioned I will follow up with a comparison of options to Project Online – and may also have some posting about individual options if any changes in behavior warrant it.  Feel free to post any questions you have!

Version history
Last update:
‎Mar 06 2019 01:04 PM
Updated by: