Task Checklists Do Not Copy

New Contributor

I love that you can copy tasks from one planner bucket to another, but when I try it the checklists do not carry over.  They appear for a second then vanish. Does anyone else have this problem? Is there a fix?

1 Reply

BTW. I figure out a workaround if anyone has this issue.

 

  1. I copy a Task within Bucket A.
  2. Then MOVE the copied Task to Bucket B.

That brings over all assignments, attachments, checklists. I was trying to copy a task, then re-assigning it to Bucket B. I was losing checklists.

 

Problem solved. 

 