Postpone tasks with dependencies

Copper Contributor

Hey folks,

 

When you postpone a maintask in asana the subtasks automatically change the start and end date as well. I was wondering if Planner 2.0 provides the same feature. 

 

Thank you in advance for you insight.

 

Kind regards

Dani

3 Replies
best response confirmed by dschweingruber1205 (Copper Contributor)
Solution

@dschweingruber1205 Hi, it happens as you set dependency between tasks. When parent tasks move, it child tasks dates gets moved automatically. Indeed this feature is available in Planner premium (planner v2.0). You need to have Project license in order to use this in Planner. 

 

Alternately, you can try Apps4.Pro Planner gantt app. This app allows to set dependency between tasks use all features as in Project app. 

@SanthoshB1 

 

Thank you for your response! That is exactly what I wanted to know.

 

Cheers, Dani

If this solution proves helpful and resolves your issue, kindly consider marking it as accepted. Doing so will aid others who encounter similar challenges in the future.
1 best response

Accepted Solutions
best response confirmed by dschweingruber1205 (Copper Contributor)
Solution

@dschweingruber1205 Hi, it happens as you set dependency between tasks. When parent tasks move, it child tasks dates gets moved automatically. Indeed this feature is available in Planner premium (planner v2.0). You need to have Project license in order to use this in Planner. 

 

Alternately, you can try Apps4.Pro Planner gantt app. This app allows to set dependency between tasks use all features as in Project app. 

View solution in original post