Apr 17 2024 02:47 PM
I am fiddling with Project for the Web / Premium Planner in an attempt to make YouTube tutorial content. I'm creating tasks, trying to make some sample content, and setting the completed/remaining hours to be partially done to simulate an in-progress project.
What I'm noticing is that the %Complete tries to auto-update, but seems to be calculating really oddly? Like it's coming out with 6% complete for 1 hr completed + 1 hr remaining = 2 hr total. Am I misinterpreting what it's trying to do or is it not functioning?
When I try to manually set the %Complete to 50% to override, it changes out the hours to be very different and it still doesn't come out right.