Hello, I am trying to create a Planner task when a Microsoft Forms is submitted. However, I keep getting the below error. I know I am doing something wrong in Update Task Details. Can someone please help me out?
Apr 22 2022 09:00 AM - edited Apr 22 2022 09:01 AM
@kanwalkheiri if you are creating a task in Planner then updating that task with the description etc you must always put in a delay action of about 10 seconds between the two. The reason is that the flow actions run so quickly that creating the planner action will not have completed before the update item tries to run, so it won't find the item.
Rob
Los Gallardos
Microsoft Power Automate Community Super User
Feb 10 2024 11:02 AM
@RobElliott I have the same issue here, and have a delay of 15 seconds. Any other reason this might be erroring?