Hi All,
Need a solution for the below. i have start and finish time but it expands to approx 8-9 days. how do i calculate total hrs with only operating hrs which starts from 4:20 am and finish at next day 1 or 2 am.
In below example i need actual value as my end result cant go with total which includes non operating hrs.
Start | Finish | Total | Operating HRs | ||||
15-06-2020 11:59:05 AM | 23-06-2020 09:06:05 AM | 189:07:00 | Sunday | 4:20 | 1:00 | ||
Monday | 4:20 | 1:00 | |||||
Actual | Tuesday | 9:06 | 1:00 | ||||
~176hrs | Wednesday | 4:20 | 1:00 | ||||
Thursday | 4:20 | 1:00 | |||||
Friday | 4:20 | 2:40 | |||||
Saturday | 4:20 | 2:40 | |||||
Jul 21 2020 05:04 PM
@Jeev125 I would say you take the total and subtract the #day * the down time but saying 1 or 2 am makes it impossible to know unless there is a complete list of hours each day or something. Furthermore your example doesn't follow your criteria. If there were 8 days and you are shutdown for at least 2am - 4:20am that is >2hrs a day or more than 16hours over 8 days which means the actual hours has to be LESS than 173 hrs and really a max of about 170 hrs but your "actual total" of ~176 hrs is MORE than that which doesn't make sense with the other data/info you gave. We, or at least I, need more clarification.
Jul 21 2020 05:15 PM
Hi @mtarler
If i take difference between start & finish time which is around ~189 as stated in table (Total), but if exclude non operating hrs from start to finish to be exact i get.
176:54:50 |
i get the actual value when i do calc for each day and sum.
what i am trying to achieve to get formula in single cell to dictate the working hrs only in compliance with Operating Hrs fro each day.
Jul 22 2020 07:11 AM
Perhaps like this
if I understood the logic correctly (can't receive 175 manually as in the grey range).
In shifts range Finish is the time on next day, i.e. =25/24 fo Sun, etc. Duration=Finish-Start.
Formula for operating time
=SUM(INDEX($I$3:$I$9,WEEKDAY(SEQUENCE(INT(C4)-INT(B4)-1,1,INT(B4)+1),1)))+
INDEX($H$3:$H$9,WEEKDAY($B$4,1))-MOD(B4,1)+
MOD(C4,1)-INDEX($G$3:$G$9,WEEKDAY($C$4,1))
assuming your version of Excel supports dynamic arrays.
Aug 05 2020 09:33 PM
Your Formula works only if there is more 2 day difference if its one day then it shows Clac Error and if its sameday then it shows Value Error.
Could you please help me with the issue.
Aug 06 2020 03:10 AM
Please check the update, formula is
=IF(INT($B4)=INT($C4),$C4-$B4,
IFERROR(SUM(INDEX($I$3:$I$9,WEEKDAY(SEQUENCE(INT(C4)-INT(B4)-1,1,INT(B4)+1),1))),0)+
INDEX($H$3:$H$9,WEEKDAY($B$4,1))-MOD(B4,1)+
MOD(C4,1)-INDEX($G$3:$G$9,WEEKDAY($C4,1)))
Aug 06 2020 05:54 PM
You are genius, but i found a small flaw, I have attach the attachment for you. Please let me know.
Aug 07 2020 07:51 AM
Sorry, forgot about overnight shifts. Will play with that bit later.