Jan 29 2024 06:32 PM
This feels like a silly question with an obvious no answer but figured I'd ask it and see if other people have tried.
I've done OS in place upgrades of my DP/MP servers and the primary SUP server. These have been done via task sequence for the in place upgrade without issues.
however I suspect I cannot use the task sequence to do the in place of the primary site server? maybe if I had a HA setup with and active passive but I do not.
Primary Site only runs:
The DP/MP's host all the data but I suspect because they have to look back to the site server they would fail in half an hour during the task sequence build.
Feb 14 2024 06:09 AM