Jan 17 2024 06:52 AM
Hello,
I have Task sequence to upgrade some application agent (This cannot be possible in a package or application installation).
The problem is that the task sequence does not work during the specified hours that I Configured.
See in Picture attached, the Assignment schedule is 20:00 time, but the deployed running on computers Earlier, without reference to the time.
How I Can configure that to run only on 20:00 time?
Thanks,
Idan.
Jan 17 2024 12:42 PM
Jan 18 2024 04:24 AM
Hello,
Thanks for your answer.
Exactly what does the log say is happening?
What does the log record mean?
The smats.log blog simply shows that the installation starts after the computer receives new policies from SCCM.
Do you have Maintenance windows?
Yes, I configure that, because I think this will help to resolve the problem. But this does not resolve.
Is it the deployment from the day before?
The deployment from a few days before.
why are you re-running the deployment daily?
I add many computers to specific collection every day to distribute the software to them.
Jan 18 2024 05:06 AM