Hello,
Planned effort for analyzed Sprint is 133.
Somehow Velocity widget is counting only 106.
The same with the Velocity widget - count of work items.
Comparing Sprint work items with Velocity widget results I can see that some of the work items were not taken into account but I have no idea why.
What could be the reason behind this discrepancy?
Thank you
Jan 07 2022 09:49 AM
Velocity chart is basing what's included in Planned Effort based on the day the Sprint started and the Stories that were in the Sprint at that time. It does not pay attention to stories that came in later. This can be adjusted somewhat on the Velocity chart configure widget to tell it how many days before Start of Sprint is the work considered final. Scroll down on the chart widget to the below and you can adjust Days past start date.
Oct 28 2022 03:22 PM
Oct 31 2022 02:28 AM
@Pawel_Wielgos Exactly as @Sherry_Hooe is mentioning, you can modify the chart behaviour as explained here in docs: https://learn.microsoft.com/en-us/azure/devops/report/dashboards/team-velocity?view=azure-devops#con...