New deploy WVD with resource manager when WVD Classic is already being used

%3CLINGO-SUB%20id%3D%22lingo-sub-1632142%22%20slang%3D%22en-US%22%3ENew%20deploy%20WVD%20with%20resource%20manager%20when%20WVD%20Classic%20is%20already%20being%20used%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-1632142%22%20slang%3D%22en-US%22%3E%3CP%3EHi%20all%2C%3C%2FP%3E%3CP%3EQuick%20Reference.%3C%2FP%3E%3CP%3EA%20new%20WVD%20can%20be%20deployed%20with%20resource%20manager%20when%20WVD%20Classic%20is%20already%20being%20used%20in%20production.%3C%2FP%3E%3CP%3EIf%20I%20register%20the%20resource%20%22Microsoft.DesktopVirtualization%22%2C%20does%20it%20affect%20WVD%20Classic%3F%3C%2FP%3E%3CP%3EThank%20you.%3C%2FP%3E%3C%2FLINGO-BODY%3E
Occasional Visitor

Hi all,

Quick Reference.

A new WVD can be deployed with resource manager when WVD Classic is already being used in production.

If I register the resource "Microsoft.DesktopVirtualization", does it affect WVD Classic?

Thank you.

1 Reply

Hi @descalier 

 

No it won't, you can have both running at the same time without any problem, they are completely separate :) 

 

Cheers

 

Neil