Timesheet Project Web App - Problem with hours/day

%3CLINGO-SUB%20id%3D%22lingo-sub-303412%22%20slang%3D%22en-US%22%3ETimesheet%20Project%20Web%20App%20-%20Problem%20with%20hours%2Fday%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-303412%22%20slang%3D%22en-US%22%3E%3CP%3EHello%20everyone%2C%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3CP%3EI%20don't%20understand%20why%20the%20number%20of%20hours%20per%20day%20in%20my%20tasks%20in%20timesheets%20in%20Project%20Web%20App%20is%207h%20per%20day%20inspite%20of%20the%20number%20of%20hours%20per%20day%20in%20my%20project's%20options%20(in%20MS%20Project)%20is%208h%2Fday%20and%20also%208h%2Fday%20in%20%22Timesheet%20Settings%20and%20Defauts%22...%3C%2FP%3E%3CP%3E%3CBR%20%2F%3ECould%20someone%20explain%20that%20to%20me%3F%3CBR%20%2F%3E%3CBR%20%2F%3EThanks%20you%20very%20much%20in%20advance%20!%3C%2FP%3E%3C%2FLINGO-BODY%3E%3CLINGO-SUB%20id%3D%22lingo-sub-335058%22%20slang%3D%22en-US%22%3ERe%3A%20Timesheet%20Project%20Web%20App%20-%20Problem%20with%20hours%2Fday%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-335058%22%20slang%3D%22en-US%22%3E%3CP%3EHi%20Colin%2C%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3CP%3ECould%20it%20be%20that%20the%20resource%20is%20available%20for%20less%20than%20100%25%20of%20his%20time%20or%20has%20a%20resource%20calendar%20setting%20of%207%20working%20hours%20per%20day%3F%26nbsp%3B%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3CP%3ECould%20you%20provide%20a%20screenshot%20of%20the%20information%20in%20the%20task%20usage%20view%20for%20this%20task%20and%20period%3F%3C%2FP%3E%3C%2FLINGO-BODY%3E
Colin_Besserer
New Contributor

Hello everyone,

 

I don't understand why the number of hours per day in my tasks in timesheets in Project Web App is 7h per day inspite of the number of hours per day in my project's options (in MS Project) is 8h/day and also 8h/day in "Timesheet Settings and Defauts"...


Could someone explain that to me?

Thanks you very much in advance !

1 Reply

Hi Colin,

 

Could it be that the resource is available for less than 100% of his time or has a resource calendar setting of 7 working hours per day? 

 

Could you provide a screenshot of the information in the task usage view for this task and period?

Related Conversations
Tabs and Dark Mode
cjc2112 in Discussions on
22 Replies
flashing a white screen while open new tab
cntvertex in Discussions on
13 Replies
Stable version of Edge insider browser
HotCakeX in Discussions on
35 Replies
How to Prevent Teams from Auto-Launch
chenrylee in Microsoft Teams on
28 Replies
IIS extension is not working - WAC 1909
HotCakeX in Windows Admin Center on
11 Replies