Home

Simple Question...Units

Highlighted
Carlos Alvarado
Occasional Visitor

Hi, 

 

I'm new to Microsoft Project and I've run into quite a few issues. Most of which I was able to solve watching videos. However, I can't seem to figure out how to change the percentage someone works per day.

 

Example: Employee A is working on a task that is 7 days long but for one of those days I want them to work 80% on a particular day while they work on something else. I've tried going into the Resource Usage View to edit it there and I thought that was working until I realized that only changed the work and did not adjust/increase for the duration of the task. 

 

Any suggestions welcomed!

1 Reply
I usually use assignment units as my starting point, then switch over to the task usage view to edit the hours by day/week/month directly. You can change the scale using the ribbon.
Related Conversations
Tabs and Dark Mode
cjc2112 in Discussions on
22 Replies
Stable version of Edge insider browser
HotCakeX in Discussions on
35 Replies
flashing a white screen while open new tab
cntvertex in Discussions on
13 Replies
How to Prevent Teams from Auto-Launch
chenrylee in Microsoft Teams on
28 Replies