Microsoft project 2016

busracopr
New Contributor

Hi all, 

 

I hope that you can help me out?

 

I am working on a project and creating a forecast for the budget and duration. During the project I want to fill in the real cost/duration, even when its higher. Is there a way to do this without the forecasted budget or duration being changed?

 

Best regards,

Bcopur

1 Reply

Hi,

You can use the baseline feature to store your original budget and estimates: https://support.office.com/en-us/article/Set-and-save-a-baseline-AC855151-34F2-42E8-8B05-C363DCED308...

Then you can use various views and reports to compare your current schedule and progress against the original one stored in the baseline.

Kind regards,

Trutz

Related Conversations
Tabs and Dark Mode
cjc2112 in Discussions on
35 Replies
Extentions Synchronization
Deleted in Discussions on
3 Replies
Stable version of Edge insider browser
HotCakeX in Discussions on
35 Replies
Security Community Webinars
Valon_Kolica in Security, Privacy & Compliance on
9 Replies
flashing a white screen while open new tab
Deleted in Discussions on
14 Replies