Timeline View, show amount of days insted of start and finish date?
In the timeline view, I would like to see the number of days each activity takes rather than the start and finish dates. How can I change that?
Sorry but the timeline text is limited to 4 items: Task Dates, Today, Timescale, and Task Progress. However, as a workaround you could concatenate the task Duration to the task Name, something like this:
John
- John-projectSilver Contributor
Sorry but the timeline text is limited to 4 items: Task Dates, Today, Timescale, and Task Progress. However, as a workaround you could concatenate the task Duration to the task Name, something like this: