Forum Discussion
Vasily_Zaytsev
Oct 21, 2021Iron Contributor
Should the capacity of a enterprise resource change daily?
We have Project Server 2019.
Should the capacity of a enterprise resource change daily in reporting database?
If we have -5 month and +36 month project server additional settings, the first record in [WSS_PWA].[pjrep].[MSP_EpmResourceByDay] be resource creation date minus 5 month and the last record be current date plus 36 month.
With best regards, Vasily.
Hi Vasily_Zaytsev ,
This will update daily, there is a job that runs each night to keep this data updated:
Paul
2 Replies
Sort By
- ware32Copper Contributor
Is it possible to set a value greater than 36?
Hi Vasily_Zaytsev ,
This will update daily, there is a job that runs each night to keep this data updated:
Paul