Project Web App and Power BI Integration
Hi, I'm trying to connect my data from Project Web App iunto Power BI but the error message, "Failed to update data source credentials: The credentials provided for the OData source are invalid....
Paul_Mather
Jun 15, 2022MVP
Hi BlissL ,
Does the account you're using having access to query the report API? In a web browser if you go to {pwaSite}/_api/ProjectData, for example https://tenant.sharepoint.com/sites/pwa/_api/ProjectData does you see the collections listed?
Paul
BlissL
Jun 15, 2022Brass Contributor
Yes, it looks like it
- Paul_MatherJun 15, 2022MVP
There is no reason on the Project Online side why this wont work then BlissL , there must be an issue on your Power BI desktop client. Can another user try on their Power BI Desktop client or you try another device if possible? This will help with next steps.
Paul