Forum Discussion
dkozhemyak
Jan 12, 2023Copper Contributor
Project Online - Approval for inclusion in the working group
Hello!
I really hope for advice.
Ours is used by Office 365 and Project Online. There is a task, it is necessary to make sure that when an employee is added to the project working group and tasks are assigned to him, these actions are previously coordinated by the line manager.
Is it possible to implement this functionality in office 365?
If this requires using any other applications, this is also suitable.
Thanks in advance for any help! ![]()
1 Reply
- dkozhemyak --
In Project for the Web (to which I believe you erroneously refer as Project Online), there is no functionality that allows a line manager or resource manager to approve resource assignments on tasks. On the other hand, if you were using Microsoft Project with Project Online, there IS functionality like this. It is known as the Resource Engagement feature. Hope this helps.