Project Managers have edit rights to all Projects
I have a strange issue where the Project Managers somehow has access(view and edit) to ALL projects (even those they are not a owner on). I have tried several things, - remove all categories (includ...
- Apr 04, 2024See if your resources have a common RBS value assigned as this can exhibit the behavior you're experiencing. Also ensure they were added as Site Collection Admin for the PWA. If this doesn't help can you elaborate on the issue? Are you using the term Project Manager to define anyone with a Plan 3 license that should be able to create/edit projects, or is that a subset of users?
RodFromm
Apr 04, 2024Steel Contributor
See if your resources have a common RBS value assigned as this can exhibit the behavior you're experiencing. Also ensure they were added as Site Collection Admin for the PWA. If this doesn't help can you elaborate on the issue? Are you using the term Project Manager to define anyone with a Plan 3 license that should be able to create/edit projects, or is that a subset of users?
- JakePApr 04, 2024Copper ContributorThanks for the response! So my permission changes to restrict access was correct. But while testing I used the delegation function. And me being a SCA, no matter what I did, the changes did not seem to work. Eventually I had a regular Project Owner test it. That worked as expected. So it was my bad.
- RodFrommApr 05, 2024Steel ContributorGlad to hear it is working correctly.