Project for the Web - Allow Team members to edit/view only his task
Hello, Project for the web - I created a project and create a security group for projects. added the team members. Assign the task to teams. Now only task owner should able to edit the percen...
- Jan 23, 2024Users with a Plan 1 or Plan 3 license with just the default Team Member permissions can edit the project in any way they want. There are few limitations to what Plan 1 license user can do, but it's limited by the license and not the assigned permissions.
We opened a ticket with Microsoft on this and they confirmed our findings that the assigned license privileges trump assigned permissions.
Paul_Mather
Dec 24, 2022MVP
Hello SBaha ,
For a user to be able to modify a project in Project for the web, the users will need one of the Project Plan licenses or Office 365 users with one of the defined licenses that allow limited edit access, details on the link below:
You'll notice users with just E1, F1 etc. will get view only access.
Hope that helps
Paul
Tingjun_Wen
Jan 25, 2023Copper Contributor
Paul Mather I have the Office 365 E3 and Project Plan 3. I created a task in Project for the Web and assigned it to myself and I did not see that this task shows up in "Assigned to me" in Planner. What else should I or the IT admin do to make this work. I am doing this test before I assign tasks to my team members and I was expecting this should work for myself as an assignee.
Thanks,
Tingjun
Thanks,
Tingjun