Forum Discussion
Chuck_Pollard
Jul 20, 2023Brass Contributor
Project; Bugs, Problems, and Issues - Timescale
This is just sketchy... I opened one of my projects and my timescale was screwy, see photo below.
When I went to fix the timescale to what my normal view looks like, I get this popup message.
Any thoughts?
1 Reply
- John-projectSilver ContributorChuck Pollard,
Since you seem to be having problems with your file, I suggest you save it as XML. Then re-open the XML file in Project. That often clears corruption. Note, you will lose any custom formatting with this process.
John