Prevent Team Members having permission to edit projects they are not part off

Hi, The Project Online configurations are set up with Project permission mode and built-in groups are mapped to AD security groups. The Categories and Global Permissions are left as OOB default setti...
  • Paul_Mather's avatar
    Nov 08, 2021

    Hello jenyalex ,

    The default permission group and categories for Team Members does prevent those users from editing projects, if the user is only a Team Member they will only be able to view those projects where they are added to the project team. The default Team Member group has just the My Tasks category added. The Team Member group category permissions for My Tasks doesn't allow edit access:

    You mentioned you are testing with a admin user who is impersonating, there are certain differences in what is / isn't displayed when using the delegation feature when the admin user is a global admin or site collection admin. Have you tried logging in and testing directly as a Team Member user rather than via delegation?

    Paul