Forum Discussion

wwelbyso's avatar
wwelbyso
Copper Contributor
Apr 27, 2023

P4W Finish to Start Dependency - Not scheduling correctly

Hi,    I have a project which has a Finish to Start dependency between 2 tasks (standard). The 2nd task should start on the next day after the first tasks, but the 2nd task is started on last day o...
  • wwelbyso's avatar
    wwelbyso
    Apr 30, 2023

    Dale_HowardMVP, thanks for the reply. I have solved my problem.
    The issue  I experienced is with the custom calendar. I defined the working time as 8am to 5pm (9 hours) instead of 8am to 4pm (8 hours). In my grid I was using days for duration of tasks, which is 8 hours not 9. The software was scheduling 8 hour tasks over 9 hour work days. As you mention, the software does not show date and time, which would have highlighted to me that the 2nd task was actually being scheduled from 4pm instead of from 8am the next morning. The Powerapp accelerator shows end date and time for a project which highlighted that the project ended at an odd time. When I changed the working time to 8am to 4pm, everything scheduled correctly. 

Resources