Forum Discussion
parlisingh
May 27, 2022Copper Contributor
MS Timeline view - Blocks in timeline view dont show progress
Hi. Using MS Project (Prof 2016) I have several tasks with mixture of of some showing progress (% work complete). The issue is that in the timeline view most of the tasks showing progress can be s...
- May 31, 2022Parlisingh,
None of the tasks under the summary line "Aspire Beta Version Workstream" have resources assigned so is there is work associated with those tasks or the summary line. A user can input any value they want in the % Work Complete field but if there is no work, there effectively is no progress. That's why you are not seeing any changes to the Timeline view.
Hope this helps.
John
John-project
May 31, 2022Silver Contributor
parlisingh,
If I may make a couple observations. First, which Aspire lines are 215 and 216? I only see the "Build Aspire Labcorp Components" summary line shown in the Timeline view and it has zero percent work complete so I wouldn't expect it to show progress.
Second, I see summary lines that have successors. It is bad practice to have links or resources assigned to summary lines. Summary lines are NOT tasks, they are simply a summary of data from performance tasks, (tasks that describe something to be done and have resources assigned to perform the effort to accomplish the task).
John
If I may make a couple observations. First, which Aspire lines are 215 and 216? I only see the "Build Aspire Labcorp Components" summary line shown in the Timeline view and it has zero percent work complete so I wouldn't expect it to show progress.
Second, I see summary lines that have successors. It is bad practice to have links or resources assigned to summary lines. Summary lines are NOT tasks, they are simply a summary of data from performance tasks, (tasks that describe something to be done and have resources assigned to perform the effort to accomplish the task).
John
parlisingh
May 31, 2022Copper Contributor
Hi, should have done with better screen shot, hadnt realised these were not captured in screen shot.
How about this:
The summary task doesn't also change the percentage done, when i increase the work complete in the sub tasks. So must be something to do with the summary line. Have tried deleting the successors tasks and still no difference
Thanks P.
- John-projectMay 31, 2022Silver ContributorParlisingh,
None of the tasks under the summary line "Aspire Beta Version Workstream" have resources assigned so is there is work associated with those tasks or the summary line. A user can input any value they want in the % Work Complete field but if there is no work, there effectively is no progress. That's why you are not seeing any changes to the Timeline view.
Hope this helps.
John- parlisinghJun 01, 2022Copper ContributorThat simple! Thank you for your help.
- John-projectJun 01, 2022Silver Contributorparlisingh,
You're welcome and thanks for the feedback.
John