Forum Discussion

parlisingh's avatar
parlisingh
Copper Contributor
May 27, 2022

MS Timeline view - Blocks in timeline view dont show progress

Hi. Using MS Project (Prof 2016) I have several tasks with mixture of of some showing progress (% work complete). The issue is that in the timeline view most of the tasks showing progress can be s...
  • John-project's avatar
    John-project
    May 31, 2022
    Parlisingh,
    None of the tasks under the summary line "Aspire Beta Version Workstream" have resources assigned so is there is work associated with those tasks or the summary line. A user can input any value they want in the % Work Complete field but if there is no work, there effectively is no progress. That's why you are not seeing any changes to the Timeline view.

    Hope this helps.
    John

Resources