jakewaze
Feb 01, 2022Copper Contributor
MS Projects Team Planner
Hi I use Projects to schedule in our work for the coming weeks/months mainly using the team planner option to visualize what each resource is working on. The issue I'm having is that if I add a re...
John-project
Feb 01, 2022Silver Contributor
jakewaze,
Project will NOT balance the workload when you add another resource to an existing task. A similar post recently appeared on the Project Answers forum. You might want to take a look:
https://answers.microsoft.com/en-us/msoffice/forum/all/peak-units-recalculation/b360525d-931e-4b38-88a2-38b7bf8edcd8
John
Project will NOT balance the workload when you add another resource to an existing task. A similar post recently appeared on the Project Answers forum. You might want to take a look:
https://answers.microsoft.com/en-us/msoffice/forum/all/peak-units-recalculation/b360525d-931e-4b38-88a2-38b7bf8edcd8
John
jakewaze
Feb 01, 2022Copper Contributor
Thanks John, I will have a read through.