Forum Discussion
jakewaze
Feb 01, 2022Copper Contributor
MS Projects Team Planner
Hi
I use Projects to schedule in our work for the coming weeks/months mainly using the team planner option to visualize what each resource is working on.
The issue I'm having is that if I add a resource to a current task, sometimes the duration doesn't reduce equally for each resource. All resources are set to the same calendar/days off etc.
Any ideas with what I could be doing wromg? Example below
- John-projectSilver Contributorjakewaze,
Project will NOT balance the workload when you add another resource to an existing task. A similar post recently appeared on the Project Answers forum. You might want to take a look:
https://answers.microsoft.com/en-us/msoffice/forum/all/peak-units-recalculation/b360525d-931e-4b38-88a2-38b7bf8edcd8
John- jakewazeCopper Contributor
Thanks John, I will have a read through.