How to enable Auto Save on Project 2016?
Hello everyone!
When I posed this question to all encompassing search engines (including MS) I get a flurry of articles telling me to go into save options and enable autosave so it saves every 5 minutes, etc.
That's not the autosave I'm looking for.
All my other office apps have a toggle button on the title bar "Autosave ON or Off" which works in conjunction with Microsoft OneDrive to automatically save your file while working, as well as provide the ability to have your office files on your local system and automatically backed up to the cloud.
I can't find any articles about how to enable this. Please advise what I am missing.
Hello EricFromNorCal ,
This feature seen below is not available in MS Project desktop:
It is just the Auto Save options here:
Paul
Hello EricFromNorCal ,
This feature seen below is not available in MS Project desktop:
It is just the Auto Save options here:
Paul
- EricFromNorCalCopper Contributor
Paul_Mather Thanks for the response, Paul! Do we know why this option is not available in MS Project?
Enabling Auto Save in the Options screen does NOT enable this slider button. Its an entirely different functionality (it just does a Save every certain number of minutes you set) It also blows away your Undo/Redo when you use this feature - so I'm not interested.
It would be great if someone from MS could chime in and explain why this feature is missing from Project, or how I can enable it.
Hello EricFromNorCal,
Yes this does work different to other office products (Word , Excel etc.) but Project is a different product to these. I'm not sure anyone from Microsoft will respond here. Probably best to raise the suggestion here: https://feedbackportal.microsoft.com/feedback/forum/40792262-301c-ec11-b6e7-0022481f8472
Paul
- EricFromNorCalCopper Contributor
Paul_Mather Thanks, but autosave option and Auto save in One Drive are two entirely different things. Any ideas when MS will get around to implementing this feature? Not sure why Project and Visio were released without them.