Forum Discussion
pauleast
Dec 05, 2019Copper Contributor
Historic RAG
Hi Does anyone know a simple way to collect historic RAG statuses etc. from Project Online? We want to show month on month changes to statuses however all reporting is 'live' - help!:) Thanks ...
Paul_Mather
MVP
Hi pauleast ,
You could build a process to push the data from all Risks lists etc. into one central list on the PWA site etc. or better still push it to something like Azure SQL DB then report of the SQL Database. There are many example 3rd party tools out there from Project partners that do this. We typically push all of the PWA data into an Azure SQL database (project, tasks, assignment, project site list data etc.) into an Azure SQL database and report from that.
Paul
pauleast
Dec 20, 2019Copper Contributor
Hi Paul_Mather
Might be a little outside of my skill set! Guessing that means there isn't a way with Flow to do this:(
Appreciate your help!:)
- Paul_MatherDec 20, 2019MVP