Chris_Hill
Mar 11, 2025Copper Contributor
Gridline for Project Start Date Shifts When Printing
Hi I have a solid gridline set for Project Start in the gridlines pop-up, which shows correctly at the project start date [Week 1] in the chart area. However when printing, including print previe...
Ignacio_Martin
Mar 11, 2025Iron Contributor
Hi Chris
In my case, with an up-to-date version (2502), Project works as you describe, and it is not what is expected.
Alternatively, you can show the Current Date or the Status Date, if you are not using it, and not show the Start Date, in the Grid option. The Current Date and the Status Date can be defined in Project > Properties > Project Information, as you may already know.
I hope I have helped you.
Ignacio
- Chris_HillMar 12, 2025Copper Contributor
Thank you Ignacio 👍