Forum Discussion
Computing tasks Finish date in Project
- Aug 22, 2023Alina_Andreica,
You need to have a custom 4h workday calendar. If it only applies to those two tasks, then use the Task Calendar field to set the 4h workday calendar for those tasks and leave the Standard calendar as your Project calendar.
Also, if the 4h workday is limited to certain tasks, do NOT change the definition of a "day" to 4 hours, leave it at the default 8h or whatever a standard day is for the rest of the tasks. Project only allows one definition of a "day" so if you have a mixed bag, I suggest you either stick with entering duration values in hours (that works for everything), or only used days in the duration field for non-4h day tasks. The 4h workday task duration will still need to entered in hours.
Understand that Project calculates all time values to the nearest minute regardless of the setting you use for duration.
John
You need to have a custom 4h workday calendar. If it only applies to those two tasks, then use the Task Calendar field to set the 4h workday calendar for those tasks and leave the Standard calendar as your Project calendar.
Also, if the 4h workday is limited to certain tasks, do NOT change the definition of a "day" to 4 hours, leave it at the default 8h or whatever a standard day is for the rest of the tasks. Project only allows one definition of a "day" so if you have a mixed bag, I suggest you either stick with entering duration values in hours (that works for everything), or only used days in the duration field for non-4h day tasks. The 4h workday task duration will still need to entered in hours.
Understand that Project calculates all time values to the nearest minute regardless of the setting you use for duration.
John
Sorry for bothering again, I've created and applied a 4h calendar for all tasks and now the number of weeks has doubled compared to what I have computed, I do not understand why
The calendar has 4h in the working days and Saturday and Sunday non-working
Thank you very much,
Alina
- John-projectAug 23, 2023Silver ContributorAlina_Andreica,
Say what? Let's start over.
1. Do you or do you not need 4h workdays for Monday through Friday for ALL your tasks?
2. What is your Project Calendar?
3. What is the Base Calendar for resource W4?
4. Do your resources have workdays that are different from the Project calendar?
5. What is the task type for T1 and T2 (i.e. fixed units, fixed work, or fixed duration)?
5. On tasks T1 and T2 what is the assignment level of the W4 resource?
John- Alina_AndreicaAug 24, 2023Copper Contributor
Thank you very much!
The project calendar was set as well to 4h but the calendar for the working resources remained Standard, therefore from the intersection with the 4h one, remained only 15-17, therefore 2h / day
Actually, I've logically deduced that from some standard specification, maybe only 2 working hours remained - and I've even thought to change the interval 15-19h to a one included in the standard working time - but didn't check the resources calendar until you recommended
It's ok now, thank you very much!
With all best wishes,
Alina
- John-projectAug 24, 2023Silver ContributorAlina,
What you are doing makes no sense to me but if it works for you, that's good.
John