Changing Task Information for Multiple Tasks - Microsoft Project Online Desktop
The version I currently use is Microsoft® Project® Online Desktop Client MSO (Version 2310 Build 16.0.16924.20054) 64-bit and I have been able to notice that the functionality to change the value of ...
- Nov 02, 2023rbuzeta,
It sounds like you got some bad information from whomever you talked to at Microsoft. The problem you report was recently reported and is apparently do to an artifact of a recent update. Please see this post:
https://techcommunity.microsoft.com/t5/project/bulk-edit-not-working/m-p/3935750
John
Mohammad2352030
Dec 27, 2023Copper Contributor
John-project
Dec 27, 2023Silver Contributor
Mohammad2352030,
If you are using the Project desktop that is part of your Project Online subscription, according to this thread, the fix has been released.
https://techcommunity.microsoft.com/t5/project/bulk-edit-not-working/m-p/3935750
However, if you are using the stand alone desktop version of Project, the fix has not yet been released although I suspect it will be within a week or two.
Update 1/5/24: For stand alone desktop users, this issue is fixed with the January 4, 2024 release of version 2312 (Build 17126.20126 CTR)
John