Basic Question - "Cost Variance" always equals "Cost"

Apologies if this is a dumb question, but I'm fairly new to Project.  I've noticed whenever I have a task that takes less time to complete than is scheduled/specified (actual duration vs duration) it...
  • Guillaume Rouyre's avatar
    Feb 03, 2021

    Hi esmitheccit,

    The variance is a calculation between a data (start, finish, work, cost, duration) and the baseline data. The baseline is a snapshot of your project so you can at any time measure the difference between what was planned and what is happening.

    So basically you need to schedule your project, save a baseline. From that the variances will be equal to 0 before you do any update. As soon as you'll update any tasks, you'll see variance.

     

    Now about progress tracking. The best practice is not to update the % complete. Because if you update the %complete to 100%, it will consider that the task took the planned work to be completed, which might not be the case. I advice that you update the actual work. Then if the actual work is less than the planned work but the task is complete, just set the remaning work to 0. It will automatically update the % complete to 100%.